Spacer Image
Home Home
 
Font size
Curve Image bulletContact Us    bulletFeedback    bulletSitemap  
   
Fortune 500 Image
 
About Us Products & Services Press & Media Investors Human Resources CSR हिन्‍दी साइट
 
Spacer Image
     
     
 
Introduction                     
Our Roots
We Believe
Our Profile
Board of Directors
Governance
Infrastructure
Major Ongoing Projects
Recognition and Awards
Chairmans Speeches
Photo Gallery
Events
 
 
     
 
 
 
 
 
Home  About Us  Major Ongoing Projects
Email to Friend Print this Page   
 

Major Ongoing Projects

 
In order to strengthen core processes and modernize, HPCL has developed ambitious plans for expansion and diversification in the areas of increasing energy demand, technological upgradation and environment management. HPCL has proposed capital expenditure (including equity investments in Joint Ventures) of Rs. 11487 Crores during the eleventh plan. Currently, several projects are in progress in different parts of India. Here is a brief introduction to these projects.
 
 
In the recent past, HPCL has commissioned some major projects like:
  • Mundra-Delhi Pipe Line (MDPL): A 1056 KM Product pipeline connecting the port of Mundra in Gujarat to Delhi with Tap-offs in between. Completed in 36 months at an cost of   Rs. 1757 Crores. Dedicated to the nation on 3rd Feb 2009
  • LPG Cavern Storage at Visakhapatnam by SALPG, a Joint Venture of HPCL: 60000 MT of LPG storage at a cost of Rs. 333 Crores, Commissioned in January 2008.
  • Visakh-Vijayawada-Secunderabad Pipe Line (VVSPL): Length of Pipeline: 571 Km, Cost: Rs. 841 Crores, Commissioned in 2002.
 
 
New FCCU at Mumbai Refinery:

HPCL is setting up New Fluidized Catalytic Cracking Unit (FCCU) at its Mumbai Refinery. Under this project new FCCU of 1.456 MMTPA with Gas concentration unit (GCU) and Flue Gas Desulphurization (FGD -158 TPH) Units of matching capacity will be installed. This will enhance the secondary processing capacity of the refinery.
 
The following major facilities are also to be made available through this project.
 
  • FCCU Feed Section consisting of feed Pre-heaters & Furnace
  • Reactor –Regeneration section consisting of catalyst circulation circuit, catalyst handling section, MAB, flue gas cooling circuit
  • Main Fractionator and Gas Concentration Unit (GCU)
  • Flue Gas Scrubbing Unit (FGSU)
  • Fuel Gas Treating Unit (FGTU) 
  • Associated utilities, DCS, Substation etc.
 
The cost of the project has been estimated at INR 900 Crores. Completion of the project (except FGD unit) is expected in July 2010.  Completion of FGD unit is expected in Sept. 2010.
 
 
Lube Oil Base Stock (LOBS) Upgradation project at Mumbai Refinery:
 
HPCL operates one of the largest Lube refineries in the country with production in the tune of 335 TMT of various Grades of API Group-1 LOBS having Sulphur above 300 ppm and saturates below 90%.
 
The market demand for LOBS quality with Sulphur below 300 ppm and saturates above 90% (i.e. API Group-II category) has increased in recent years. Hence HPCL is working to upgrade the production of LOBS quality up to 200 TMT per annum of  API Group II category with a capability to produce API Gr-III under the Lube Oil Base Stock Quality Upgradation project. .
 
The cost of this project has been estimated at INR 1030 Crores.
 
The project is expected to be completed by June 2010.
 
 
Diesel Hydro Treating (DHT) at Mumbai & Visakhapatnam Refineries:
 
HPCL is setting up Diesel Hydrotreater Units of 2.2 MMTPA each with associated facilities at Mumbai Refinery (MR) and Visakhapatnam Refinery (VR) to meet Euro-IV specifications for diesel as per the latest Auto Fuel Policy.
 
The Environmental clearance for the DHT projects for Mumbai Refinery and Visakh Refinery have been obtained.
 
The cost of the project is estimated at INR 3284 Crores for Mumbai Refinery and INR 3597 Crores for Visakhapatnam Refinery. The projects are expected to be completed by Sept 2011.
 
 
 
Single Point Mooring (SPM) Project at Visakh Refinery:
 
Visakh Refinery is putting up a SPM project to facilitate unloading of large crude parcels of the size of around 300,000 Metric Tonnes from Very Large Crude Carriers (VLCCs). The VLCCs cannot be berthed in the existing crude receiving jetties due to draught restrictions.
 
The installation of SPM will reduce the freight cost and wharfage charges and thus will improve the economics of the Refinery. The cost of this project has been estimated at about INR 643 Crores
 
The Environmental Clearance for this project has been obtained. The offshore and onshore installation work of the project has been completed.
 
 
 
Resitement of Visakhapatnam Terminal
 
In order to provide additional ground area to Visakh Refinery for setting up facilities to produce green fuels, it is proposed to shift the adjacently located marketing facilities consisting of POL terminals and LPG Plant.  The scope of the green field project consists of setting up of new Black oil, White oil and LPG facilities in the plots acquired from VPT.
 
Black Oil facilities include setting up of about 94,000 KL storage tanks and two tank truck gantries of 8 bays each to handle Bitumen, Furnace oil (FO), Low Sulphur Heavy stock (LSHS), Light Diesel Oil (LDO) Jute Batching Oil (JBO) and High Flash HSD (HF HSD).
 
White Oil facilities include storage of about 1,68,000 KL Motor Spirit (MS), High Speed Diesel (HSD), Naphtha & Aviation Turbine Fuel (ATF), two tank truck loading gantries of 8 bays each and a single spur T/W gantry to load 46 BTPN tank wagons.
 
LPG facilities include setting up of mounded storage of about 4,400 MT capacity to store LPG, Auto LPG and Propylene, a single spur tank wagon gantry to load 32 BTPN TG wagons and bottling facilities of capacity 88,000MTPA.
 
The total project cost is about Rs 750 Cr. and the completion schedule is as under:
  • Black Oil Terminal: December 2010
  • White Oil Terminal: Dec 2011
  • LPG Facilities: March 2011
 
Guru Gobind Singh Refinery Products Evacuation Project (GGSRPEP)
 
Hindustan Mittal Energy Ltd. (HMEL), a Joint Venture Company of HPCL with M/s Mittal Energy Investments Pte Ltd is setting up a Green field State of the Art 9 MMTPA capacity refinery at Bathinda in Punjab. Marketing of products of GGSR is entrusted with HPCL.
 

A new storage cum dispatch terminal is being put up near the refinery at Raman Mandi for receiving POL products (MS, HSD, SKO & ATF) from the refinery and further pumping into two product pipelines.

  • Raman Mandi - Bathinda Pipeline (10” dia, 30 km long with a capacity of approximately 1.37 MMTPA)

  • Raman Mandi - Bahadurgarh Pipeline. (18” dia, 250 km long with a capacity of approximately 4.71 MMTPA)
 
The estimated cost of the project is Rs 605 Crores. The project is scheduled for completion by March 2011.
 
 
 
Ennore Terminal
 
HPCL is setting up a Greenfield Oil Terminal at Ennore, located in northern outskirts of Chennai City. Ennore is approx. 30 Kms. away from Chennai City and falls under Tiruvalur district of Tamil Nadu. This is relocation of the existing facilities at Tondiarpet, Chennai.
 

The terminal shall have tankages of capacity 1,40,000 KL for storage and dispatch of products of Motor Spirit (MS), High Speed Diesel (HSD), Superior Kerosene Oil (SKO) and Aviation Turbine Fuel (ATF).

 

Project includes setting up of  facilities including tankages, Tank Truck loading facility, Tank Wagon loading/ receipt facility along with product receipt facilities from the Ennore Port and Chennai Petroleum Corporation Ltd (CPCL). The tank farm and Tank Truck Loading operations will be fully automated.

 
The total project cost is about Rs 224 Cr. and the scheduled completion is February 2011.
 
 
   Copyright 2008, HPCL. All rights reserved.

HPCL Stock Price   |   Privacy Policy   |   Terms of Use   |   Disclaimer         

Web Support Image
Best viewed by 1024 x 768 pixel resolution with Internet Explorer 5.5 and above.